AET Engineers wraps up piping installation at Corbox Liloan, Cebu Plant

CEBU CITY. The AET Engineering team recently completed the construction and installation of piping works last December 2019 at Corbox Liloan, Cebu plant. The project started on 1st week of September and completed on the 3rd week of December which is earlier than the contract duration of 4 months.

The piping system is an additional steam line for the plant’s new manufacturing line. The project covers the tapping of steam from the main boiler header to the distribution lines for the new manufacturing line  of the plant. The project construction includes all the pipe connections, valve installations, insulations, testing and commissioning.